During a Yelm City Council meeting on Tuesday, Oct. 13, councilors unanimously approved a development agreement with Yelm MPC LLC to establish a long-term framework for the creation of the city’s 640-acre property as a master planned community.
The agreement between the City of Yelm and Yelm MPC LLC addresses development standards, project phasing, residential and commercial development, parks and open space, emergency services, transportation improvements, utilities, public infrastructure, mitigation requirements and the respective responsibilities of both parties.
A big component of the development agreement is the timing, construction and financing of Tahoma Boulevard and other transportation improvements needed to serve the development, according to the Yelm City Council packet from Tuesday, Oct. 13.
The agreement also establishes both parties’ responsibilities for major water-system infrastructure needed to serve the development, including the addition of a water tower and well, along with a pond.
The development agreement presented during the Yelm City Council meeting on Tuesday, Oct. 13, is the product of months of negotiations between the City of Yelm and the developer, with assistance from the City of Yelm’s legal counsel, consultants, engineers and other professionals.
Councilor Tracey Wood was curious about the name change from Blue Fern Development to Yelm MPC LLC in the development agreement. Duana Koloušková, Chief Legal Officer on behalf of the applicant, said this is how the developer has to set up their different corporate roles.
She noted this changes “absolutely nothing” about their responsibilities under the development agreement. Blue Fern Development still exists, but Yelm MPC LLC is a “uniquely formed” liability corporation. Koloušková believes this is what Yelm wants for the property at stake.
“It’s a funny thing. We had to essentially set up appropriate legal entities for our projects,” Koloušková said. “We are not unique in this. Before my role with Blue Fern, I represented builders and developers for nearly 30-years, and every single applicant does exactly this.”
Councilor Griselda Arias said she’s not an expert in all of the development talks pertaining to the 640 acres, but based on what she understands, she wanted to understand how the traffic element fits together.
“Mitigation can be reviewed during the SEPA process or even during traffic impact review, which we are currently going back and forth with their traffic agent,” Yelm Public Services Director Cody Colt said. “They’ve submitted a report and we’re about to provide a response back to their most recent traffic report.”
He added that through each phase of development, Blue Fern might have to do different litigation processes.
Prior to the Yelm City Councilors commenting on the development agreement, members of the community had the opportunity to testify for or against the development of the 640-acre property.
During the community comments portion of the segment, several community members addressed that the proposed 640-acre property currently sits within the Rainier School District (RSD).
Councilor Joseph Richardson attested to the concerns about RSD’s potential role in all of this.
“It sounds like there’s a lot of moving parts here. We’ve got to honor our neighbor, Rainier, and it’s always important to acknowledge that,” Richardson said. “Before you ask someone to dance, you have to have a conversation. What I’m hearing is Rainier needs the capital facilities plan in order to have a conversation first. Then, development agreement is second to that and is prior to any type of mitigation that is possible. Correct?”